Cuyahoga County: Construction update

Sign up for email updates or follow the Ohio Department of Transportation (ODOT) District 12 on Facebook or Twitter for current Cuyahoga County highway construction information.

 

For the week of August 4, 2021

Construction updates are available 24-hours-a-day at www.OHGO.com

 

Interstate Projects

I-71 Cuyahoga County

Interstate 71 resurfacing – Resurface I-71 between W. 117th St. and I-480 and ramps at W. 150th St., W. 130th St., and Bellaire Rd. in Cleveland. Estimated Completion: mid-August 2022

  • I-71 between I-480 and W. 117th St. has various weekend lane restrictions and ramp closures through mid-August 2022.

Interstate 71 median, lighting, and sign repairs – Various median, lighting, and sign repairs along I-71 in Cuyahoga County. Estimated Completion: June 2023

  • I-71 between I-480 and U.S. 42 (Pearl Rd.) will have various nightly lane restrictions through November for maintenance of traffic shift.

I-77 Cuyahoga County

Interstate 77 resurfacing – Resurface I-77 between Oakes Rd. and Rockside Rd. in Brecksville, Broadview Heights, and Independence. Estimated Completion: mid-August 2022

  • I-77 between Oakes Rd. and Rockside Rd. has various nightly lane restrictions through mid-August 2022 for resurfacing.

I-90 Cuyahoga County

Interstate 90 and State Route 252 (Columbia Rd.) interchange improvements - Improve the northern half of the I-90 westbound and SR 252 (Columbia Rd.) interchange in the city of Westlake. Estimated Completion: October 2022

  • Sperry Rd. just east of SR 252 (Columbia Rd.) has various lane restrictions.
  • I-90 westbound to Columbia Rd. southbound is closed through September.
    • Detour will use the I-90 westbound to Columbia Rd. northbound ramp to access southbound Columbia Rd.

Interstate 90 bridge rehabilitation – Rehabilitate and paint the bridges on I-90 between E. 136th St. and E. 156th St., E. 140th St. and E. 152nd St. under I-90 in Cleveland. Estimated completion: August 2022

  • I-90 eastbound and westbound between Lakeshore Blvd. and E. 185th St. will have various nightly lane restrictions and ramp closures for pavement repairs through late August.
  • E. 152nd St. and E. 140th St. under I-90, and the E. 140th St. and E. 152nd St. connector roads will have various off-peak lane restrictions and closures through late August.

Interstate 271 Cuyahoga County

Interstate 271 Express Lanes resurfacing – Resurface the I-271 express lanes between I-480 and U.S. 322 in in the cities of Beachwood, Lyndhurst, Mayfield Heights, Pepper Pike, Warrensville Heights, and Village of Orange. Estimated Completion: late October 2022

  • I-271 southbound express lanes at Mayfield Rd. is closed nightly between 7:30 p.m. and 6 a.m. through October for resurfacing.
    • Detour will utilize I-271 local lanes.
  • I-271 northbound express lanes at I-480 is closed nightly between 7:30 p.m. and 6 a.m. through October for resurfacing.
    • Detour will utilize I-271 local lanes.

Interstate 480 Cuyahoga County

Interstate 480 pavement replacement and ramp re-alignment - Pavement replacement on I-480 and SR 176 interchange, interchange re-alignment on I-480 eastbound ramp to SR 176, and SR 17 (Brookpark Rd.) ramps to I-480 east/west in Cleveland and Brooklyn Heights. Estimated Completion: November 2022

NEW IMPACTS

  • The following closures will be in place Wednesday, August 17, at 11 p.m. through Thursday, August 18, at 6 a.m.
    • SR 176 northbound between Brookpark Rd. and Schaff Rd.
      • Detour will be Brookpark Rd. westbound to State Rd. northbound to I-480 eastbound to SR 176 northbound.
    • SR 176 southbound between Scaff Rd. and Brookpark Rd.
      • Detour will be SR 176 southbound to I-480 westbound to State Rd. southbound to Brookpark Rd. eastbound.

Interstate 480 Lane Addition - Add a fourth lane on I-480 westbound between the SR 14 (Broadway Ave.) entrance and exit ramps Estimated Completion: October 2022

  • I-480 westbound at SR 14 (Broadway Ave.) traffic is shifted so work can progress in the middle lane. Access to the Transportation Blvd. will be maintained. This traffic pattern will be in place through late August.
  • SR 14 (Broadway Ave.) to I-480 westbound is closed through October 2022.
    • Detour will be I-480 eastbound to Warrensville Rd. to I-480 westbound.

Interstate 480 Valley View Bridge Deck Replacement - Construct a new bridge between the two existing Valley View bridges and replace the decks of the I-480 east and westbound Valley View bridges in Garfield Heights and Independence. To learn more about the project click here. Estimated Completion: June 2024

NEW IMPACTS

  • Canal Rd. between Rockside Rd. and Granger Rd. will have various nightly lane restrictions maintained by a flagger between 6 p.m. and 6 a.m. beginning on Monday, August 15, through Friday, August 26, for resurfacing.

CONTINUING IMPACTS

  • All I-480 westbound traffic will officially be traveling on the new I-480 Valley View Bridge through summer 2022 as crews work on the existing I-480 westbound bridge. Westbound traffic will still have access to the I-77 interchange and exit to Transportation Blvd.

Interstate 480 Noise Wall – Construct a noise wall on I-480 between Sterns Rd. and SR 252 in North Olmsted. Estimated Completion: October 2022

  • I-480 between SR 252 and Sterns Rd. has various lane restrictions and shoulder closures through late October for noise wall construction.

Interstate 480 Slope Repair – I-480 westbound between Tiedeman Rd. and Southwood Dr. has various shoulder closures and lane restrictions through late August for slope repairs. Estimated Completion: October 2022

Interstate 490 Cuyahoga County

Interstate 490/State Route 10/Opportunity Corridor Section 3 - Construction a new roadway between E. 55th St./I-490 and E. 93rd St. in the city of Cleveland. Visit www.opportunitycorridor.transportation.ohio.gov for more information and detours. Estimated Completion: December 2022

U.S. and State Route Projects

Cuyahoga County

U.S. Route 6 and 20 (Euclid Ave.) resurfacing and safety improvements –U.S. 6 and U.S. 20 (Euclid Ave.) between I-90 and Upper Valley Dr. in the City of Euclid will be reduced to one lane in each direction with a two-way center turn lane through October for resurfacing and safety improvements. Estimated Completion: October 2022

U.S. Route 6 (Lake Ave.) resurfacing –U.S. 6 (Lake Ave.) between SR 252 (Columbia Rd.) and just west of Brandon Pl. in Bay Village has various lane restrictions for resurfacing through September. Estimated Completion: September 2022

U.S. Route 42 (Pearl Rd.) resurfacing –U.S. 42 (Pearl Rd.) between just north of Ridge Rd. and just south of Snow Rd. is reduced to one lane in each direction through October 2022, for resurfacing. Estimated Completion: mid-October 2022

U.S. Route 422 (Kinsman Rd.) intersection improvements and widening – Intersection improvements and widening on U.S. 422 (Kinsman Rd.) at E. 93rd St. Estimated Completion: October 2022

The following closures are in place for truck traffic through August.

  • E.93rd St. to Kinsman Rd. eastbound
    • Detour will be Buckeye Rd. east to Shaker Blvd. east to E116th St.
  • E.93rd St. to Kinsman Rd. westbound
    • Detour will be E. 93rd St. south to Union Ave. west to E. 78th St.
  • U.S. 422 (Kinsman Rd.) at E. 93rd St. has various lane restrictions for intersection improvements and widening through October 2022

U.S. Route 422 resurfacing – Resurface U.S. 422 between SR 175 (Richmond Rd.) and Solon Rd. in Warrensville Heights, Solon, and Village of Orange. Estimated Completion: October 2022

  • U.S. 422 westbound and eastbound between SR 91 and SR 175 (Richmond Rd.) has various nightly lane restrictions between 9 p.m. and 6 a.m. through October for resurfacing.

State Route 3 (Ridge Rd.) resurfacing –SR 3 (Ridge Rd.) between SR 82 (Royalton Rd.) and just south of Craigleigh Dr. in North Royalton is reduced to one lane in each direction through September. Estimated Completion: September 2022

State Route 17 (Brookpark Rd.) pavement repairs and resurfacing – SR 17 (Brookpark Rd.) between SR 10 (Lorain Rd.) and Clague Rd. will have various lane restrictions in North Olmsted for pavement repairs.  Estimated Completion: November 2022

State Route 17 resurfacing – SR 17 (Libby Rd. and Bartlett Rd.) between SR 8 (Northfield Rd.) and SR 43 (Aurora Rd.) in the city of Bedford Heights is reduced to one lane in each direction through October for resurfacing. Estimated Completion: October 2022

State Route 21 (Brecksville Rd.) bridge rehabilitation - Rehabilitate the SR 21 (Brecksville Rd.) over I-480 bridge in the city of Independence. Estimated Completion: June 2023

  • SR 21 (Brecksville Rd.) over I-480 is reduced to one lane in each direction with a traffic pattern shift through November 2022.
  • I-480 under SR 21 (Brecksville Rd.) will have various nightly lane restrictions through late October.

State Route 82 (Royalton Rd.) bridge replacement –SR 82 at Scottsdale Dr. in Broadview Heights has various lane restrictions through October for a bridge replacement. Estimated Completion: October 2022

SR 91 (SOM Center Rd.) resurfacing –SR 91 (SOM Center Rd.) between Cedar Rd. and U.S. 322 (Mayfield Rd.) in Mayfield Heights and Gates Mills has various lane restrictions maintained by flaggers, through August for resurfacing. Estimated Completion: August 2022

Ashton Ln. bridge replacement –Ashton Ln. over Porter Creek in Bay Village is closed through August for a bridge replacement. Estimated Completion: August 2022

  • Detour is Bradley Rd. to Wolf Rd. to Bassett Rd.

Cedar Rd. resurfacing – Cedar Rd. between S. Taylor Rd. to S. Green Rd. in University Heights and South Euclid is reduced to one lane in each direction through October for resurfacing. Estimated Completion: October 2022

Center St. bridge rehabilitation – Center St. bridge over the Cuyahoga River between Merwin Ave. and Detroit Ave. in Cleveland is closed through late October 2022, for bridge rehabilitation. Estimated Completion: November 2022

  • Detour is Main Ave. to W. 25th St. to Columbus Rd.

E.75th St. over the Norfolk Southern/GCRTA railroads bridge replacement – E. 75th St. over the Norfolk Southern/GCRTA railroad in Cleveland is closed through October 2022 for bridge replacement. Estimated Completion: May 2023

E. 185th St. rehabilitation and streetscape improvements – Pavement rehabilitation and streetscape improvements to E. 185th St. between Lake Erie and Pawnee Ave. Estimated Completion: October 2023

NEW IMPACTS

  • Pawnee Rd. from E. 185th to Lake Erie will be reduced to northbound traffic only. Southbound traffic will be closed beginning on Friday, August 12, through mid-November for pavement work.
    • Detour will be Lake Shore Blvd. to E. 200th St. to St. Clair Ave.
  • Villaview Rd. between Neff Rd. and E. 185th will be reduced to westbound traffic only. Eastbound traffic will be closed beginning on Monday, August 15, through mid-November for pavement work.
    • Detour via Neff Rd.

CONTINUING IMPACTS

  • Locherie Rd. at E. 185th St. is permanently closed.
  • E.185th St. between Lake Erie and Abbey Ave. is reduced to northbound traffic only through fall 2022 for pavement rehabilitation and streetscape improvements. On street parking for northbound traffic will be maintained.
    • Detour for southbound traffic will be Lake Shore Blvd. to E. 200th St. to St. Clair Ave.

Scranton Rd. bridge deck replacement - Replace the bridge deck on Scranton Rd. bridge over I-90 in the city of Cleveland. Estimated Completion: November 2022

  • Scranton Rd. bridge over I-90 is reduced to northbound traffic only. Southbound traffic is closed.
    • Detour is Barber Ave. to W. 25th St. to Clark Ave.

W. Franklin Blvd. resurfacing and roundabout construction – Resurfacing and roundabout construction at eight intersections on W. Franklin Blvd. between W. 85th St. and W. 25th St. in Cleveland.  Estimated Completion:  August 2023

  • W. Franklin Blvd. to W. 58th St. and W. 50th St. southbound is closed through mid-August for roadway construction.
    • Detour will be W. 65th St. to Detroit Ave. to Lorain Ave.
  • W. Franklin Blvd. between W. 85th St. and W. 50th St. is reduced to westbound traffic only through October 2022 for resurfacing and roundabout construction.
    • Detour for eastbound traffic will be W. 85th St. to Detroit Ave. to W. 50th St.

Various Locations

Various intersection improvement in Mayfield Heights – The following locations in the city of Mayfield Heights has various daily lane restrictions for intersection improvements through September. Estimated Completion: late September

  • Ridgebury Blvd. at Mayfield Heights High School
  • SR 91 (SOM Center Rd.) at Woodhawk Dr./Gates Mills Blvd.
  • SR 91 (SOM Center Rd.) at Ridgebury Blvd.
  • U.S. 322 (Mayfield Rd.) at Chelmsford Rd.
  • Mayfield Rd. at SR 91 (SOM Center Rd.)

Minor Bridge Repairs and Painting along I-90 – Various bridge repairs and painting along I-90 in Cuyahoga County. Estimated Completion: October 2023

  • I-90 over the Rocky River has various off peak lane restrictions for bridge repairs and painting through October 2022.

Cuyahoga County Bridge Repairs – Various bridge repairs in Cuyahoga County

  • U.S. 422 eastbound over SR 91 has various lane restrictions through late August.
  • SR 91 to U.S. 422 eastbound is closed through mid-August for bridge repairs.
    • Detour is U.S. 422 westbound to Harper Rd. to U.S. 422 east.
  • Cyprus Dr. pedestrian bridge over I-480 is closed, through late August for bridge repairs.
  • W. 220th St. over I-480 is closed through early August for bridge repairs.
    • Detour will be Mastick Rd. to W. 210th St. to SR 10/Lorain Rd.
  • W.130th to I-480 eastbound is closed through November.
    • Detour will utilize Brookpark Rd.
  • I-480 westbound to W. 130th St. is closed through November.
    • Detour will utilize W. 150th St.
  • I-480 westbound over W.130th will have a traffic pattern shift and various lane restrictions through November for bridge work. 
  • U.S. 42 between Brookside Park Dr. and Bradwell Ave. is reduced to one lane in each direction through October 2022 for various bridge repairs. 
  • Turney Rd. over I-480 is shifted onto the east side of the bridge through late August for bridge repairs. One lane of traffic will be maintained in each direction.  
  • I-271 southbound express lanes under Fairmount Blvd. will be reduced to one lane nightly between 7:30 p.m. and 6 a.m. for bridge work through late October.  