Cuyahoga County: Construction update

Sign up for email updates or follow the Ohio Department of Transportation (ODOT) District 12 on Facebook or Twitter for current Cuyahoga County highway construction information.

 

For the week of May 12, 2021

Construction updates are available 24-hours-a-day at www.OHGO.com

 

Interstate Projects

I-71 Cuyahoga County

Interstate 71 resurfacing – Resurface I-71 between W. 117th St. and I-480 and ramps at W. 150th St., W. 130th St., and Bellaire Rd. in Cleveland. Estimated Completion: late May 2022

  • I-71 between I-480 and W. 117th St. has various weekend lane restrictions and ramp closures through late May 2022.

I-77 Cuyahoga County

Interstate 77 resurfacing – Resurface I-77 between Oakes Rd. and Rockside Rd. in Brecksville, Broadview Heights, and Independence. Estimated Completion: July 2022

  • I-77 between Oakes Rd. and Rockside Rd. has various nightly lane restrictions through spring 2022 for resurfacing.

I-90 Cuyahoga County

Interstate 90 and State Route 252 (Columbia Rd.) interchange improvements - Improve the northern half of the I-90 westbound and SR 252 (Columbia Rd.) interchange in the city of Westlake. Estimated Completion: October 2022

  • Sperry Rd. just east of SR 252 (Columbia Rd.) is limited to eastbound traffic only through June for interchange improvements.
    • Detour for Sperry Rd. westbound is Clague Rd. to Detroit Rd. to Columbia Rd.
  • I-90 westbound to Columbia Rd. southbound will be closed beginning on Sunday, May 1, at 8 p.m. through September.
    • Detour will use the I-90 westbound to Columbia Rd. northbound ramp to access southbound Columbia Rd.

Interstate 90 bridge rehabilitation – Rehabilitate and paint the bridges on I-90 between E. 136th St. and E. 156th St., E. 140th St. and E. 152nd St. under I-90 in Cleveland. Estimated completion: July 2022

NEW IMPACTS

  • I-90 eastbound and westbound between Lakeshore Blvd. and E. 185th St. will have various nightly lane restrictions and ramp closures for pavement repairs through Saturday, May 14.

CONTINUING IMPACTS

  • E. 152nd St. and E. 140th St. under I-90, and the E. 140th St. and E. 152nd St. connector roads will have various off-peak lane restrictions and closures through mid-May.

Interstate 271 Cuyahoga County

Interstate 271 resurfacing – Resurface I-271 between Mayfield Rd. and I-90 in Highland Heights, Willoughby Hills, and the Village of Mayfield.  Estimated Completion late May 2022

  • I-271 between Mayfield Rd. and I-90 has various off-peak lane restrictions through late May 2022.

Interstate 480 Cuyahoga County

Interstate 480 bridge painting - Paint the I-480 bridge over the Rocky River and SR 10 (Lorain Rd.) bridge over the Rocky River in Cleveland. Estimated Completion: June 2022

NEW IMPACTS

  • Valley Pkwy. under Lorain Rd. will be reduced to one lane maintained by a temporary traffic signal beginning on Monday, May 16, through Saturday, May 21, for bridge painting.

Interstate 480 pavement replacement and ramp re-alignment - Pavement replacement on I-480 and SR 176 interchange, interchange re-alignment on I-480 eastbound ramp to SR 176, and SR 17 (Brookpark Rd.) ramps to I-480 east/west in Cleveland and Brooklyn Heights. Estimated Completion: November 2022

  • Granger Rd/Brookpark Rd. ramp to I-480 eastbound is closed through spring 2022, for pavement work.
    • Detour is west on Brookpark Rd., north on State Rd. to I-480 eastbound.
  • Brookpark Rd. eastbound between Broadview Rd. and W. 10th St. has various lane restrictions.

Interstate 480 Lane Addition - Add a fourth lane on I-480 westbound between the SR 14 (Broadway Ave.) entrance and exit ramps Estimated Completion: October 2022

  • SR 14 (Broadway Ave.) to I-480 westbound is closed through October 2022.
    • Detour will be I-480 eastbound to Warrensville Rd. to I-480 westbound.
  • I-480 westbound under SR 14 (Broadway Ave.) ramps will have various nightly and weekend lane restrictions through mid-April.

Interstate 480 Valley View Bridge Deck Replacement - Construct a new bridge between the two existing Valley View bridges and replace the decks of the I-480 east and westbound Valley View bridges in Garfield Heights and Independence. To learn more about the project click here. Estimated Completion: June 2024

  • All I-480 westbound traffic will officially be traveling on the new I-480 Valley View Bridge through summer 2022 as crews work on the existing I-480 westbound bridge. Westbound traffic will still have access to the I-77 interchange and exit to Transportation Blvd.

Interstate 480 Resurfacing – Resurface I-480 between Lee Rd. and I-271 in Bedford Heights, Cleveland, Maple Heights, and Warrensville Heights. Estimated Completion: late May 2022

  • I-480 between Lee Rd. and I-271 will have various off-peak restrictions and ramp closures through late May 2022 for resurfacing.

Interstate 480 Noise Wall – Construct a noise wall on I-480 between Sterns Rd. and SR 252 in North Olmsted. Estimated Completion: October 2022

  • I-480 between SR 252 and Sterns Rd. has various lane restrictions and shoulder closures through late October for noise wall construction.

Interstate 490 Cuyahoga County

Interstate 490/State Route 10/Opportunity Corridor Section 3 - Construction a new roadway between E. 55th St./I-490 and E. 93rd St. in the city of Cleveland. Visit www.opportunitycorridor.transportation.ohio.gov for more information and detours. Estimated Completion: June 2022

U.S. and State Route Projects

Cuyahoga County

U.S. Route 6 and 20 (Euclid Ave.) resurfacing and safety improvements NEW IMPACTS U.S. 6 and U.S. 20 (Euclid Ave.) between I-90 and Upper Valley Dr. in the City of Euclid will be reduced to one lane in each direction with a two-way center turn lane beginning on Thursday, May 12, through October for resurfacing and safety improvements. Estimated Completion: October 2022

U.S. Route 42 (Pearl Rd.) resurfacing –U.S. 42 (Pearl Rd.) between just north of Ridge Rd. and just south of Snow Rd. is reduced to one lane in each direction through October 2022, for resurfacing. Estimated Completion: mid-October 2022

U.S. Route 422 (Kinsman Rd.) intersection improvements and widening – Intersection improvements and widening on U.S. 422 (Kinsman Rd.) at E. 93rd St. Estimated Completion: October 2022

The following closures are in place for truck traffic through August.

  • E.93rd St. to Kinsman Rd. eastbound
    • Detour will be Buckeye Rd. east to Shaker Blvd. east to E116th St.
  • E.93rd St. to Kinsman Rd. westbound
    • Detour will be E. 93rd St. south to Union Ave. west to E. 78th St.
  • U.S. 422 (Kinsman Rd.) at E. 93rd St. has various lane restrictions for intersection improvements and widening through October 2022

State Route 14 (Broadway Ave.) resurfacing SR 14 (Broadway Ave.) between McCracken Rd. and E. 104th St.in Garfield Heights has various lane restrictions through June for resurfacing. Estimated Completion: June 2022

State Route 17 (Brookpark Rd.) pavement repairs and resurfacing – The project resurfaces and makes pavement repairs on SR 17 (Brookpark Rd.) between SR 10 (Lorain Rd.) and Clague Rd. in North Olmsted.  Estimated Completion: June 2022

State Route 17 resurfacing –SR 17 (Libby Rd. and Bartlett Rd.) between SR 8 (Northfield Rd.) and SR 43 (Aurora Rd.) in the city of Bedford Heights is reduced to one lane in each direction through October for resurfacing. Estimated Completion: October 2022

State Route 21 (Brecksville Rd.) bridge rehabilitation Rehabilitate the SR 21 (Brecksville Rd.) over I-480 bridge in the city of Independence. Estimated Completion: June 2023

  • SR 21 (Brecksville Rd.) over I-480 is reduced to one lane in each direction with a traffic pattern shift through November 2022.
  • I-480 under SR 21 (Brecksville Rd.) will have various nightly lane restrictions through late October.

State Route 82 (Royalton Rd.) bridge replacement NEW IMPACTS SR 82 at Scottsdale Dr. in Broadview Heights will have various lane restrictions beginning on Wednesday, May 18, through October for a bridge replacement. Estimated Completion: October 2022

State Route 175 (Richmond Rd.) intersection improvements –SR 175 (Richmond Rd.) and Mayfield Rd. intersection in Lyndhurst has various daily lane restrictions through May 2022, for traffic signal and pavement improvements. Estimated Completion: May 2022

Cedar Rd. resurfacing – Cedar Rd. between S. Taylor Rd. to S. Green Rd. in University Heights and South Euclid is reduced to one lane in each direction through October for resurfacing. Estimated Completion: October 2022

Center St. bridge rehabilitation – Center St. bridge over the Cuyahoga River between Merwin Ave. and Detroit Ave. in Cleveland is closed through late October 2022, for bridge rehabilitation. Estimated Completion: November 2022

          Detour is Main Ave. to W. 25th St. to Columbus Rd.

E.75th St. over the Norfolk Southern/GCRTA railroads bridge replacement – E. 75th St. over the Norfolk Southern/GCRTA railroad in Cleveland is closed through October 2022 for bridge replacement. Estimated Completion: May 2023

E. 185th St. rehabilitation and streetscape improvements – Pavement rehabilitation and streetscape improvements to E. 185th St. between Lake Erie and Pawnee Ave. Estimated Completion : October 2023

NEW IMPACTS

  • E.185th St. between Lake Erie and Abbey Ave. will be reduced to northbound traffic only beginning on Monday, May 16, through fall 2022 for pavement rehabilitation and streetscape improvements. On street parking for northbound traffic will be maintained.
    • Detour for southbound traffic will be Lake Shore Blvd. to E. 200th St. to St. Clair Ave.

Scranton Rd. bridge deck replacement - Replace the bridge deck on Scranton Rd. bridge over I-90 in the city of Cleveland. Estimated Completion: June 2022

  • Scranton Rd. bridge over I-90 is reduced to northbound traffic only. Southbound traffic is closed.
    • Detour is Barber Ave. to W. 25th St. to Clark Ave.

Union Ave. resurfacing - Union Ave. between E. 116th St. and Kinsman Rd. in Cleveland has various lane restrictions. Estimated Completion: June 2022

  • Union Ave. between E. 116th St. and Kinsman Rd. is reduced to eastbound traffic only. Westbound traffic is closed through late of May.
    • Detour will be Kinsman Rd. to E. 116th St. to Union Ave.

W. Franklin Blvd. resurfacing and roundabout construction – Resurfacing and roundabout construction at eight intersections on W. Franklin Blvd. between W. 85th St. and W. 25th St. in Cleveland.  Estimated Completion:  August 2023

  • W. Franklin Blvd. between W. 85th St. and W. 50th St. is reduced to westbound traffic only through October 2022 for resurfacing and roundabout construction.
    • Detour for eastbound traffic will be W. 85th St. to Detroit Ave. to W. 50th St.

Various Locations

Various Paving Repairs in District 12 – Various pavement repairs in District 12. Estimated Completion: October 2022

  • I-90 between Kirtland Rd. and Blair Rd. has various lane restrictions for pavement repairs, through late May.

I-271 and I-90 Bridge Painting in Cuyahoga County – Various bridge painting along I-271 and I-90 in Cuyahoga County.  Estimated Completion: October 2022

NEW IMPACTS

  • Rockefeller Rd. over I-90 will have various lane restrictions beginning on Monday, May 16, through late June for bridge painting.

Minor Bridge Repairs and Painting along I-90 – Various bridge repairs and painting along I-90 in Cuyahoga County. Estimated Completion: October 2023

  • Valley Pkwy. under I-90 has various lane restrictions for bridge painting and minor bridge repairs through July.

Cuyahoga County Bridge Repairs – Various bridge repairs in Cuyahoga County

NEW IMPACTS

  • W.130th to I-480 eastbound will be closed beginning on Friday, May 13, at 8 p.m. through November.
    • Detour will utilize Brookpark Rd.
  • I-480 westbound to W. 130th St. will be closed beginning on Friday, May 13, at 8 p.m. through November.
    • Detour will utilize W. 150th St.
  • U.S. 422 eastbound over Solon Rd. will be reduced to one lane beginning on Friday, May 27, through late June for bridge repairs.
  • SR 91 to U.S. 422 eastbound will be closed beginning on Friday, May 27, through late June for bridge repairs.
    • Detour U.S. 422 westbound to Harper Rd. to U.S. 422 east.
  • I-71 between U.S. 42 and Snow Rd. will have various nightly lane restrictions for bridge repairs beginning on Wednesday, May 18, through Wednesday, May 25, for bridge repairs.

CONTINUING IMPACTS

  • I-480 westbound and eastbound over W.130th will have a traffic pattern shift and various lane restrictions through November for bridge work. 
  • U.S. 42 between Brookside Park Dr. and Bradwell Ave. is reduced to one lane in each direction through October 2022 for various bridge repairs. 
  • I-77 under Oakes Rd. will have various shoulder closures through late May for bridge repairs. 
  • Turney Rd. over I-480 is shifted onto the west side of the bridge through mid-June for bridge repairs. One lane of traffic will be maintained in each direction.  
  • I-271 southbound express lanes under Fairmount Blvd. will be reduced to one lane nightly between 7:30 p.m. and 6 a.m. for bridge work through late May.  
  • I-480 under Turney Rd. and Transportation Blvd. has various nightly lane restrictions between 8 p.m. and 6 a.m. through late May for bridge repairs.  
  •  I-271 local lanes and express lanes under Fairmount Blvd. has various nightly lane closures between 7 p.m. and 6 a.m. through late May for bridge work. 
  • Transportation Blvd. northbound and southbound over I-480 is shifted onto the west side of the bridge through spring 2022 for bridge repairs. Two lanes of traffic will be maintained in each direction.