Stark County: Construction update

Week of December 12, 2022

Stark County (Thursday, December 8, 2022) – The following construction projects are anticipated to affect highways in Stark County next week. All scheduled work is weather permitting.

 

Interstate 77 & U.S. 30 reconstruction, Canton – pavement replacement on I-77 at U.S. 30. Project includes bridge replacement on I-77 just north of U.S. 30 and the ramp bridge from U.S. 30 westbound to I-77 northbound. Estimated completion, June 2024.
CONTINUING IMPACTS

  • The ramp from I-77 northbound to U.S. 30 westbound is closed through spring 2023. The detour is I-77 northbound to State Route 800 exit then re-enter I-77 northbound to U.S. 30 eastbound to Cherry Ave. to U.S. 30 westbound.
  • The ramp from U.S. 30 east to I-77 north is closed through fall of 2023 for bridge rehabilitation and construction. The detour is U.S. 30 east to Cherry Ave. to US 30 west to I-77 north.
  • The ramp from Cherry Ave. south to US 30 west is closed through fall of 2023. The detour is Cherry Ave. south to 11th St. east to US 30 west.
  • The right lane of I-77 north is closed just south of Deuber Ave. SW. The ramp to State Route 800 will remain open.
  • Traffic wishing to proceed on I-77 northbound should use the left lane. I-77 north may exit at State Route 800. This is the I-77 north alternate route between State Route 800 and State Route 172. The route is I-77 north to State Route 800, re-enter I-77 north to U.S. 30 east to Cherry Ave. to U.S. 30 west to I-77 north.
  • Traffic on I-77 southbound between State Route 172 and State Route 800 is shifted right, to allow for new bridge construction. Traffic will remain in this configuration until late spring 2023.

 

U.S. 62 & State Route 153 resurfacing in Canton & Louisville
US 62 between Columbus Rd. and California Ave. has various lane restrictions. Estimated completion, late December 2022.

 

U.S. 62T resurfacing and bridge replacements, Alliance
SR 225 over U.S. 62T is closed through late January for a bridge removal. The detour for SR 225 southbound is US 62T westbound to Beeson St. to U.S. 62T eastbound to SR 225.The detour for SR 225 northbound is SR 183 northbound to U.S. 224 to SR 225 southbound. Estimated completion, November 2023.

 

U.S. 62 relocation, City of Canton & Canton Township
The following restriction and ramp closures are in place through late fall 2022:

  • Traffic on U.S. 62 between SR 43/Market Ave. and Harrisburg Rd. has been placed on the newly constructed U.S. 62 pavement.
  • The ramp from SR 43/Market Ave. to U.S. 62 eastbound is closed through early winter 2023. The detour is SR 43 to 55th St. to Harmont Ave. to U.S. 62.

Estimated completion, October 2024.

 

State Route 172 intersection improvements, Perry Township
The following routes have various lane restrictions for signal final project work:

  • SR 172 between Sippo Ave. and Saratoga Ave.
  • Perry Dr. at SR 172

Estimated completion, mid-December 2022.

 

State Route 241 widening, Massillon
SR 241 between SR 172 and Hills and Dales Rd. is reduced to one lane daily and maintained by flaggers for waterline installation and widening. Estimated completion, late summer 2024.