WEEK OF MAY 28, 2023
All outlined work is weather permitting. Visit OHGO.com for travel updates or follow the Ohio Department of Transportation (ODOT) District 6 on Facebook or Twitter for current construction information on the Downtown Ramp Up project.
Interstates 70/71 Reconstruction – I-70/71 will experience lane restrictions through downtown Columbus to widen and reconstruct the roadway, replace bridges over the interstate, rebuild ramps, and construct new urban avenues parallel to the interstate. Various downtown ramps will permanently close. Estimated completion: Fall 2025
For more information about the Downtown Ramp Up project please visit ohgo.com/7071.
NEW IMPACTS
-
The Cleveland Ave. ramp to I-71 southbound will close nightly (7 p.m. - 5 a.m.) starting Tuesday, May 30 through Friday, June 2.
-
Detour: Cleveland Ave. to I-71 northbound to 11th Ave. to I-71 southbound
-
-
The I-670 eastbound ramp to I-71 southbound will close nightly (8 p.m. - 5 a.m.) starting Tuesday, May 30 through Friday, June 2.
-
Detour: I-670 eastbound to I-71 northbound to 11th Ave. to I-71 southbound
-
-
I-71 southbound between I-670 and Main St. will have various overnight lane restrictions (8 p.m. - 5 a.m.) starting Tuesday, May 30 through Friday, June 2.
-
I-71 northbound between I-70 and I-670 will have various overnight lane restrictions (9 p.m. - 5 a.m.) starting Tuesday, May 30 through Friday, June 2.
CONTINUING IMPACTS
- Souder Ave. between Mound St. and Thomas Ave. closed starting June 20, 2022 for one year.
- Southbound detour: Davis Ave. northbound to Sullivant Ave. westbound to Glenwood Ave. southbound to Mound St. eastbound
- Northbound detour: Mound St. westbound to Glenwood Ave. northbound to Sullivant Ave. eastbound.
- The I-70 eastbound exit ramp to Front St. closed permanently June 17, 2022 so crews can construct a new exit ramp. The detour is I-70 east to Livingston Ave. to N. 4th St. to W. Mound St. to High St. or Front St. To access the Franklin County Court House parking garage on Front St., drivers should follow the detour to southbound High St. and continue to Sycamore St. to northbound Front St.
- W. Fulton St. closed permanently June 17, 2022 between Short St. and Ludlow St.
- Livingston Ave. closed to through traffic at City Park Ave. on June 17, 2022 until Fall 2024. Traffic coming from the exit ramp will not be impacted.
- The traffic pattern on the ramp from SR 315 south to I-70 east changed June 17, 2022. Instead of SR 315 south traffic remaining in its own lane to join I-70 east, traffic coming from SR 315 south will have to merge with I-70 east traffic. This pattern will be in effect for a little more than a year.
- Beginning October 7th, Front St. converted to two-way traffic between W. Mound St. and W. Fulton St.
- The Front St. bridge over I-70 closed Saturday, October 29 for bridge replacement until Spring 2025.
- Detour: W. Sycamore St. to High St. to Mound St. OR Main St. to High St. to W. Sycamore St.
- The I-70 westbound ramp to SR 315 northbound closed Saturday, March 25 for 6 months.
- Detour: I-70 westbound to Rich/Town St. exit to SR 315 northbound.
- SR 315 northbound traffic will need to use U.S. 33 to SR 315 southbound to access downtown.
To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed, and watch for stopped traffic while passing through the work zone. Remember, move over or slow down.