Cuyahoga County: Construction update

Sign up for email updates or follow the Ohio Department of Transportation (ODOT) District 12 on Facebook or Twitter for current Cuyahoga County highway construction information.

 

For the week of December 3, 2020

Construction updates are available 24-hours-a-day at www.OHGO.com

 

Interstate Projects


I-71 Cuyahoga County

Interstate 71 lane addition and retaining wall (CCG7A)  – Construct a new deacceleration lane on I-71 southbound to SR 176 ramp and construct a new retaining wall. For more information about this and other Innerbelt Modernization Plan projects please visit www.Innerbelt.org.   Estimated Completion:  June 2021.

  • I-71 southbound exit to SR 176 southbound has various lane restrictions.

I-77 Cuyahoga County

Interstate 77 Widening over Interstate 490, (CCG6A) bridge widening – Widen and replace I-77 bridge over I-490 in Cleveland. Estimated completion: early December.  For more information about this and other Innerbelt Modernization Plan projects please visit www.Innerbelt.org.

  • I-77 northbound and southbound over I-490 has various lane restrictions for paving work.

I-90 Cuyahoga County

Interstate 90 sign repair – Sign structure repairs on I-90 at various locations in Cuyahoga County. Estimate completion: Fall 2020

The following lane restrictions and closures will be in place on Thursday, December 3, through Friday, December 4, between 8 p.m. and 2 a.m. for overhead sign repairs.

  • I-90 between Lakeshore Blvd. and E. 260th St. will have various lane restrictions.
  • I-90 eastbound exit ramp to E. 260th St. will be closed.
  • I-90 eastbound at E. 260th St. will have a short duration closure lasting no longer 10 minutes.

Interstate 90 bridge rehabilitation – Rehabilitate and paint the bridges on I-90 between E. 136th St. and E. 156th St., E. 140th St. and E. 152nd St. under I-90 in Cleveland. Estimated completion: July 2022

  • E. 152nd St. under I-90, and the Waterloo Rd. and S. Waterloo Rd. connector roads will have various off-peak lane restrictions.

Interstate 90 bridge rehabilitation – Bridge deck replacement and bridge painting on I-90 at E. 185th St., Neff Rd., and E. 200th St. in Cleveland. Estimated completion: early December

  • E. 185th St., Neff Rd., and E. 200th St. under I-90 will have various lane restrictions.

Interstate 90 interchange improvements - Traffic flow improvements on Martin Luther King Jr. Dr. at the I-90 interchange and modify the I-90 east and westbound exit ramps to Martin Luther King Jr. Dr. in Cleveland. Estimated completion: mid December 2020

  • Martin Luther King Jr. Dr. and I-90 interchange will have various daily lane restrictions.

Interstate 90 sign repair – Sign structure repairs on I-90 at various locations in Cuyahoga County. Estimate completion: Fall 2020

  • I-90 between Lakeshore Blvd. and E. 260th St. will have various lane restrictions.

Interstate 90 resurfacing and pavement repairs – Pavement resurfacing and pavement repairs on I-90 between the Rocky River and W. 65th St. in the cities of Cleveland and Lakewood. Estimated completion: mid December.

  • I-90 between the Rocky River and W. 65th St. will have various lane restrictions for pavement work through mid December 2020.
     

I-271 Cuyahoga/Lake counties

Interstate 271 ramp re-alignment Replace and re-align the ramp from I-271 northbound to I-90 westbound and replace two bridges on I-271 between Eddy Rd. and I-90 in Willoughby Hills. Estimated Completion: September 2021

NEW IMPACTS

The following closure will be in place on Thursday, December 3, through Friday, December 4, for bridge beam placement.

  • I-271 northbound express lanes at I-90 –will be closed between 7 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.

The following closures will be in place on Friday, December 4, through Saturday, December 5, for bridge beam placement.

  • I-271 northbound local lanes at I-90 – will be closed between 9 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.
  • I-271 northbound express lanes at I-90 –will be closed between 7 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.

The following closure will be in place nightly on Monday, December 7, through Wednesday, December 9, between 7 p.m. and 6 am. for bridge beam placement.

  • I-271 northbound express lanes at I-90 –will be closed between 7 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.

The following closures will be in place nightly on Wednesday, December 9, through Friday, December 11, between 7 p.m. and 6 am. for bridge beam placement.

  • I-271 southbound express lanes at SR 91 will be closed.
    • The detour will be I-271 southbound local lanes.
  • I-271 northbound express lanes at I-90 –will be closed between 7 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.

The following closures will be in place on Friday, December 11, through Saturday, December 12, between 7 p.m. and 6 am. for bridge beam placement.

  • I-271 northbound local lanes at I-90 – will be closed between 9 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.
  • I-271 northbound express lanes at I-90 –will be closed between 7 p.m. and 6 a.m.
    • The detour will be I-90 west to Bishop Rd. to I-90 east to I-271 north.

Eddy Rd. between Bishop Rd. and Som Center Rd. is closed for overhead bridge work through Friday, December 4, at 5 p.m.

    • Traffic will be detoured via Chardon Rd.

CONTINUING IMPACTS

  • I-271 northbound and southbound (express lanes) between just south of Eddy Rd. and I-90 are shifted to the right.

Interstate 271 widening - Full-depth pavement replacement, widening and bridge work on I-271 north and southbound between the Cuyahoga/Summit county line and Miles Rd. in Bedford, Bedford Heights, Warrensville Heights, and Oakwood. Estimated Completion: late-fall 2020

  • Work will require various off-peak lane closures on I-271 between the Summit County line and Miles Rd.

Interstate 480 Cuyahoga County

Interstate 480 bridge painting - Paint the I-480 bridge over the Rocky River and SR 10 (Lorain Rd.) bridge over the Rocky River in Cleveland. Estimated Completion: June 2022

  • SR 10 (Lorain Rd.) eastbound over the Rocky River has various lane restrictions for bridge painting, through mid-December.
  • I-480 eastbound over the Rocky River has various lane restrictions for bridge painting through spring 2021.

Interstate 480 resurfacing – Resurface I-480 between the Lorain County line and Rocky River bridge in North Olmsted and Fairview Park. Estimated Completion: mid-December 2020

  • I-480 between the Lorain County line and the Rocky River bridge - will have various nightly lane restriction for pavement work beginning Monday, November 30, through mid-December.

Interstate 480 Valley View Bridge Deck Replacement - Construct a new bridge between the two existing Valley View bridges and replaces the decks of the I-480 east and westbound Valley View bridges in Garfield Heights and Independence. To learn more about the project click here. Estimated Completion: June 2024

  • All I-480 eastbound traffic will officially be traveling on the new I-480 Valley View Bridge through Fall 2021 as crews work on the existing I-480 eastbound bridge. Eastbound traffic will still have access to the I-77 interchange and exit to Transportation Blvd.

Interstate 490 Cuyahoga County

Interstate 490/State Route 10/Opportunity Corridor Section 3 - Construction a new roadway between E. 55th St./I-490 and E. 93rd St. in the city of Cleveland. Visit www.opportunitycorridor.transportation.ohio.gov for more information and detours. Estimated Completion: June 2022

  • E. 89th St. between Woodland Ave. and Kennedy Ave. is permanently closed.
    • The detour to access Kennedy Ave. will be Buckeye Rd.
  • Tennyson Rd. between Buckeye Rd. and Evarts Rd. is permanently closed. Traffic will be re-routed via Grand Ave.
  • Colfax between E. 68th St. and E. 69th St. and E. 68th St. between Kinsman Rd. and Colfax Rd. are permanently closed.
  • E. 55th St. between Bragg Rd. and Bower Ave. is restricted to one lane in each direction.
  • I-490 is closed between I-77 and E. 55th St. through June 2021.
  • Short term lane and road closures on various side streets will also be necessary. Details will be forthcoming.
  • E. 79th St. between Woodland Ave. and Holton Ave. will be closed through early December.
    • Detour will be Woodland Ave. to E. 75th St. to Holton Ave.
    • Pedestrian traffic will be maintained along the west side of E. 79th St.

 

U.S. and State Route Projects

Cuyahoga County

U.S. 6 (Detroit-Superior) Bridge over the Cuyahoga River bridge repairs - Merwin Ave. under U.S. 6 (Detroit-Superior) bridge is closed for overhead bridge repairs in Cleveland. Estimated Completion: October 2021.

U.S. 42 (Pearl Rd.) resurfacing and pavement repairs – This project performs resurfacing and pavement repairs on U.S. 42 (Pearl Rd.) in Middleburg Heights, Parma, Parma Heights and Strongsville. Estimated Completion: June 2021

  • U.S. 42 (Pearl Rd.) between Fowles Rd. to W. 130th St. will have various lane restrictions through late August.

State Route 3 (Ridge Rd.), pavement repairs and resurfacing - SR 3 (Ridge Rd.) between Pleasant Valley Rd. and U.S. 42 (Pearl Rd.) in Parma will have various daily lane restrictions to perform pavement repairs. Estimated Completion: late April 2021
 

State Route 43 (Miles Ave.) resurfacing – The project resurfaces SR 43 (Miles Ave.) between Broadway Ave. and E. 175th St. in Cleveland, curb, sidewalk repairs as well as traffic signal work. Estimated Completion: spring 2021

  • SR 43 (Miles Ave.) between E. 131st St. and Lee Rd. in Cleveland has various lane restrictions for resurfacing work.
    • Eastbound traffic will be detoured via E. 131st St to Harvard Ave. to Lee Rd. to Miles Ave.

State Route 174 (Chagrin River Rd.) slope repairs – The project will repair the slope on the east side of Chagrin River Rd., just south of the Rodgers Rd. intersection in Gates Mills. Estimated Completion: December 2020.

  • SR 174 on the east side of Chagrin River Rd., just south of Rodgers Rd. is reduced to one lane of traffic through December 2020 for slope repairs.

Clark Ave. resurfacing - The project resurfaces Clark Ave. between W. 41st St. and Quigley Rd. Work also includes drainage and waterline maintenance, traffic signal work, pavement repairs and streetscape improvements. Estimated Completion: early December

  • Clark Ave. between W. 41th St. and Quigley Rd. has various lane restrictions for pavement work through early December 2020

West Huron Road (Tower City) bridge maintenance - W. Prospect Ave. in Cleveland is closed to westbound traffic. Work includes bridge joint replacement, bridge deck resurfacing and sealing, and sidewalk replacement on W. Huron Rd., W. Prospect Ave., W. 6th St., W. 3rd St. and W. 2nd St. Estimated Completion: early December.

  • W. Huron Rd. between Ontario St. and W.6th St. is reduced to one of traffic in each direction for roadway repairs through early December.