Medina County: Construction update

Week of May 10, 2021

MEDINA COUNTY (Thursday, May 6, 2021) – The following construction projects are anticipated to affect highways in Medina County next week. All outlined work is weather permitting.


North Carpenter Road major reconstruction - North Carpenter Road, between SR 303 and Boston Road, will have single lane closures to complete remaining project work. Work includes, but is not limited to, smoothness milling, sidewalk work, landscaping, permanent pavement markings, and punch list items. All remaining work will be completed utilizing daily lane closures and flaggers. Estimated completion: June 2021


State Route 3 resurfacing – State Route 3, from Medina city limits to I-76, will have single lane closures for a resurfacing project. Traffic will be maintained by flaggers. Estimated completion: August 2021


State Route 3 northbound closure – State Route 3, between Fenn Road and Hamilton Road, is closed to northbound traffic for pavement reconstruction. THE ROAD IS ONLY OPEN TO SOUTHBOUND TRAFFIC. The detour route for northbound traffic is SR 3 to U.S. 42, north on U.S. 42 to SR 303, east on SR 303 to I-71, south on I-71 to SR 3.

CONTINUING IMPACTS

  • Remsen Road, between SR 3 and Church Road, is closed for intersection reconstruction work. The detour route will be west on Remsen Road to Old Weymouth Road, south on Old Weymouth Road to SR 3, south on SR 3 to Hamlin Road, north on Hamlin Road to Remsen Road, and reverse. Estimated completion: Tuesday, May 11, 2021

Estimated completion of entire project: Friday, August 27, 2021


U.S. Route 42 bridge replacement – U.S. 42, between Crawford Road and SR 421/U.S. 224, is closed for a bridge replacement project. The detour route for southbound motorists is U.S. 42 to U.S. 224, west on U.S. 224 to SR 301, south on SR 301 to U.S. 42 and reverse for northbound motorists. Estimated completion: Wednesday, July 21, 2021


I-71 resurfacing – I-71 northbound and southbound, at the I-71/I-76 interchange, will have nightly lane closures for pavement repairs. Crews will be completing pavement removal with resurfacing to follow. Estimated completion: August 2021


State Route 83 railroad repairs – State Route 83, between Seville Road and Greenwich Road, is closed for railroad crossing repairs. The detour route for northbound motorists will be SR 83 to I-71, north on I-71 to U.S. 224, west on U.S. 224 to SR 421, west on SR 421 to SR 83, and reverse for southbound motorists. Estimated completion: Saturday, May 8, 2021


State Route 94 culvert replacement – State Route 94, just north of SR 18, will close Monday, May 10 for a culvert replacement. The detour route for northbound motorists will be SR 94 to SR 18, west on SR 18 to I-71, north on I-71 to I-271, north on I-271 to SR 94, and reverse for southbound motorists. Estimated completion: Friday, May 14, 2021


State Route 94 culvert replacement – NEW IMPACTSState Route 94, just south of Forest Drive, will close Monday, May 17 for a culvert replacement. The detour route for northbound motorists will be SR 94 to SR 18, west on SR 18 to I-71, north on I-71 to I-271, north on I-271 to SR 94, and reverse for southbound motorists. Estimated completion: Friday, May 21, 2021


State Route 162 bridge replacement – State Route 162, between State Road and Burdett Road, is closed for a bridge replacement project. The detour route for eastbound motorists is SR 162 to SR 94, north on SR 94 to SR 18, east on SR 18 to I-77, south on I-77 to SR 21, south on SR 21 to SR 162, and reverse for westbound motorists. Estimated completion: Sunday, June 20, 2021