U.S. 68 reconstruction

Roadway Major Rehab

Project Status

  1. Proposed

  2. In Development

  3. Pre-construction

  4. Construction

  5. Completion

Project information

Project location:  U.S. 68 in the village of Arlington

Construction project cost: 

Phase 2: $1.34 million

Phase 3: $857,298

Contractor:  Helms and Sons Excavating, Findlay (both phases)

 

Reason for the project 

  • The pavement of U.S. 68 was built in the 1910s and 1920s. The original brick base remains beneath much of the pavement through the village.
  • The base beneath the pavement is poorly drained which leads to frequent pavement failures and repairs.

 

Project summary

Phase 1

  • Completed in 2018
  • Reconstructed U.S. 68 (Main Street) from Liberty Street to the bridge over Buck Run, including curb and gutter, drainage and storm sewer.
  • Cost: $915,868

Phase 2

  • Reconstruct the pavement on U.S. 68 (Main Street) from the south corporation limit to Liberty Street.
  • Reconstruct curb, gutter, drainage, and storm sewer.
  • Will close on June 1 May 18 for approximately four months. 

Phase 3

  • Reconstruct the pavement on U.S. 68 (Main Street) from Buck Run to just north of Wardwell Street.
  • Reconstruct curb, gutter, drainage, and storm sewer.
  • Will close on May 4 for approximately four months.

 

Project schedule

  • Work will begin in May 2020.
    • Phase 3 will close on May 4 for approximately four months.
    • Phase 2 will close on June 1  May 18 for approximately four months.

 

  • The highway reopened on Saturday, September 5, 2020.
  • Expected completion is late fall.

 

Maintenance of traffic

  • The route is open. Lane restrictions may occur for finish work.

 

 

 

View Project's Public Comments ()

Public comments regarding our projects are always welcome!

This section is for frequently asked questions and project-related questions. You may notice that some projects require one or more formal comment period(s) with deadlines for comments to be considered during certain phase(s) of the project development process. Typically called the “public comment period," this is when ODOT asks the public for input before an important decision needs to be made, such as choosing a preferred alternative. You may notice these periods generally occur immediately following a public meeting.

All comments received, regardless of when or how they are submitted, will be reviewed and considered and/or responded to by the ODOT project team. Comments received through this forum will, when appropriate, be publicly posted along with ODOT’s response; Such comments will be moderated to remove personal information prior to posting.

Please let us know if you have questions, and thank you for your interest and input on the project! 