The Ohio Department of Transportation (ODOT) invites you to participate in a virtual public meeting for the proposed improvement of U.S. Route 20 (North Ridge Road) between State Route 2 and State Route 528 (Hubbard Road) in Painesville, Perry, and Madison townships and North Perry Village in Lake County. To comply with Governor DeWine’s guidelines regarding limiting social gatherings in response to COVID-19, the meeting will be conducted online or by phone only. 

Thursday, December 3, 2020
Presentation at 5:00 p.m. followed by Q&A Session
Join online: https://publicinput.com/S8172
Join by phone: 855-925-2801, meeting code 4635
 

Individuals who require interpretation services or a reasonable accommodation to participate in this meeting should contact me, no later than November 18, 2020. Public participation is solicited without regard to race, color, sex, age, national origin, or disability.

Si desea que los materiales para esta reunión son traducidos a español, contacte a Christine Rosa tan pronto que sea posible a Christine.Rosa@dot.ohio.gov o por teléfono a 216-584-2001.

Public input is important and provides valuable feedback that helps guide decision-making through all phases of development. All materials presented during the virtual meeting will be available on this project webpage. If you would like these materials mailed to you, please, contact D12.Public.Information@dot.ohio.gov.

We encourage comments to be submitted here on the project website. They can also be submitted via email, phone or mail to: 

Tom Sorge, ODOT District 12
5500 Transportation Blvd.
Garfield Heights, Ohio 44125
Phone: 216-584-2086
Email: Tom.Sorge@dot.ohio.gov

We ask that comments be submitted by January 4, 2021.

Project Information:

Based on current and future pavement conditions ratings on U.S. 20 (North Ridge Rd.) in eastern Lake County, this major rehabilitation work is necessary to address the long-term integrity of the driving surface. The project will also replace all catch basins  and improve the drainage along this corridor. Pavements are designed for a 20 years of vehicle traffic, but with routine maintenance, can last up to 50 years and longer.

This project involves the full reconstruction and widening of the roadway with a new asphalt pavement section.  The roadway will be widened from an existing width of 44’ to a proposed width of 50’. The pavement will be widened from 4-10’ lanes to one 12’ and one 11’ lane with a 2’ shoulder in each direction. These are the minimum lane and shoulder widths permitted.


The project also includes the installation of a new storm sewer system, catch basins, curb, and gutter section to better control drainage on the pavement and meet current design standards.

All existing signalized intersections with turn lanes will remain and they will not be reconstructed within the limits of the existing signalized intersections with turn lanes, but the roadway will be resurfaced. There is no proposed work to be completed on the existing signals within the limits of this project except for the existing signal at DeRubertis Driv

During construction, one lane of traffic will be maintained in each direction at all times.Side streets will be closed for a short duration to complete work. Anticipate less than 30 days with alternating sides streets being closed. The following side streets will remain open during construction:

  • Townline Road
  • McMackin Road
  • Green Road
  • DeRubertis Drive
  • SR 528 - Hubbard Road

Project will be constructed in two sections: 

  • Townline Road to Green Road
  • Green Road to SR 528/Hubbard Road 

Construction is estimated to begin spring 2023 and be complete in fall 2025.

Right-of-Way
Permanent right-of-way will be required for this project to accommodate the new drainage system, drainage outlet improvements, utility pole relocations, fire hydrant relocations, reconstruction of driveways, and roadway grading associated with pavement widening. ODOT will need to purchase new right-of-way from 59 parcels within the project limits. Acquisition is expected to begin in January 2021 and will take approximately 12 months until acquisition is complete in January 2022.

For more information on major rehabilitation process on U.S. 20 between SR 2 and Townline Rd. (PID 108665), click here

View Project's Public Comments ()

Public comments regarding our projects are always welcome!

This section is for frequently asked questions and project-related questions. You may notice that some projects require one or more formal comment period(s) with deadlines for comments to be considered during certain phase(s) of the project development process. Typically called the “public comment period," this is when ODOT asks the public for input before an important decision needs to be made, such as choosing a preferred alternative. You may notice these periods generally occur immediately following a public meeting.

All comments received, regardless of when or how they are submitted, will be reviewed and considered and/or responded to by the ODOT project team. Comments received through this forum will, when appropriate, be publicly posted along with ODOT’s response; Such comments will be moderated to remove personal information prior to posting.

Please let us know if you have questions, and thank you for your interest and input on the project! 