I-77 and U.S. 30 interchange improvements

Bridge Preservation

Project Status

  1. Proposed

  2. In Development

  3. Pre-construction

  4. Construction

  5. Completion

About the project

This $56 million project will make pavement and bridge repairs along I-77 and U.S. 30 in the city of Canton. Work will include:

  • Replacement of two bridges, including the ramp from US 30 westbound to I-77 northbound over West Nimishillen Creek and the I-77 bridge over West Nimishillen Creek within the US 30 and I-77 interchange.
  • Major rehabilitation of the I-77 bridge over Market Avenue, 15th Street and Cleveland Avenue, just south of the I-77 and U.S. 30 interchange.
  • Full-depth pavement replacement on I-77 within its interchange with U.S. 30 and the resurfacing of I-77 from just north of state Route 800 to the I-77 and U.S. 30 interchange.
  • Minor bridge maintenance work to 15 structures along U.S. 30, U.S. 62, and I-77.
  • Replacement of the concrete median barrier guardrail with concrete barrier, lighting upgrades, signing, and pavement markings.

The entire project is scheduled to be completed by summer 2023.

Timeline

Phase 1 (Summer 2019 – Summer 2020)

See detour map for Phase 1

I-77 northbound traffic will be maintained in the existing two travel lanes.

The ramp from US 30 westbound to I-77 northbound will be closed for two 45-day periods, and on four separate weekends.

  • Traffic will be detoured onto U.S. 30 eastbound to I-77 southbound to state Route 800 back to I-77 northbound.


Phase 2 (Summer 2020 – Fall 2020)

See detour map for Phase 2

Two lanes of traffic on I-77 northbound and southbound will be maintained at all times during peak travel times.

The ramp from U.S. 30 eastbound to I-77 northbound will be closed to traffic and detoured.

  • Traffic will be detoured onto U.S. 30 eastbound through the Cherry Avenue loop ramps onto U.S. 30 westbound back to I-77 northbound, or I-77 southbound to state Route 800 back to I-77 northbound

The ramp from Cherry Avenue to U.S. 30 westbound will be closed to traffic and detoured.

  • Traffic will be detoured onto 11th Street back to U.S. 30 westbound.


Phase 3 (Fall 2020 – Fall 2021)

See detour map for Phase 3

The I-77 northbound median travel lane will be shifted to the southbound side of the median (contraflow lane) and the outside northbound lane will be diverted to the Cherry Avenue detour route.

The ramp from U.S. 30 eastbound to I-77 northbound will be closed. 

  • Traffic will be detoured onto U.S. 30 eastbound through the Cherry Avenue loop ramps to US 30 westbound back to I-77 northbound.

The ramp from I-77 northbound to U.S. 30 westbound will be closed.

  • Traffic will be detoured onto I-77 northbound through the Cherry Avenue loop ramps back to U.S. 30 westbound.

The ramp from Cherry Avenue to U.S. 30 westbound will be closed.

  • Traffic will be detoured onto 11th Street back to U.S. 30 westbound.


Phase 4 (Fall 2021 – Fall 2022)

See detour map for Phase 4

I-77 southbound traffic will maintain two lanes by being shifted over a crossover to I-77 northbound. I-77 northbound travel lane will be shifted to the outside shoulder to maintain one lane. The outside northbound lane will continue to be diverted to the Cherry Avenue loop ramps.

US 30 westbound to I-77 northbound will be open to traffic.

The ramp from U.S. 30 eastbound to I-77 northbound will be closed. 

  • Traffic will be detoured onto U.S. 30 eastbound through the Cherry Avenue loop ramps to US 30 westbound back to I-77 northbound.

The ramp from I-77 northbound to U.S. 30 westbound will be closed.

  • Traffic will be detoured onto I-77 northbound through the Cherry Avenue loop ramps back to U.S. 30 westbound.

The ramp from Cherry Avenue to U.S. 30 westbound will be closed.

  • Traffic will be detoured onto 11th Street back to U.S. 30 westbound.


Phase 5 (Fall 2022 – Summer 2023)

See detour map for Phase 5

I-77 northbound and southbound traffic will be shifted onto the outside shoulders to maintain two lanes in each direction.  

The ramp from U.S. 30 eastbound to I-77 northbound will be closed. 

  • Traffic will be detoured onto U.S. 30 eastbound through the Cherry Avenue loop ramps to US 30 westbound back to I-77 northbound.

View Project's Public Comments ()

Public comments regarding our projects are always welcome!

This section is for frequently asked questions and project-related questions. You may notice that some projects require one or more formal comment period(s) with deadlines for comments to be considered during certain phase(s) of the project development process. Typically called the “public comment period," this is when ODOT asks the public for input before an important decision needs to be made, such as choosing a preferred alternative. You may notice these periods generally occur immediately following a public meeting.

All comments received, regardless of when or how they are submitted, will be reviewed and considered and/or responded to by the ODOT project team. Comments received through this forum will, when appropriate, be publicly posted along with ODOT’s response; Such comments will be moderated to remove personal information prior to posting.

Please let us know if you have questions, and thank you for your interest and input on the project! 

Filter by Area of Interest

You can filter this list filtering with the topics on the list below.

Leave a Comment